Are
you uncertain about whether to go forward with a particular construction
project on a certain site? If so, before spending money on due diligence,
you’ll want to make a smaller, timelier investment known as a
feasibility study.
Determining whether a potential site will work for a project is one
of the primary reasons owners and developers choose to conduct feasibility
studies before buying land or building on their existing sites. Among
other things, feasibility studies can also tell you whether your project
is financially feasible and whether the locale’s regulatory structure
will allow it.
When Schaedler Yesco Distribution, Inc., grew out of its central warehouse
facility in Harrisburg, PA, the company didn’t know whether its
city location could accommodate the additional 40,000 square feet it
needed, which would almost double the current space. After hiring two
different contractors to conduct feasibility studies, Schaedler Yesco
possessed the information and ideas it needed to make a decision. “We
realized we could get enough space to stay here for at least 10 years,”
says CEO Jim Schaedler.
Worth the Investment
You can pay from a few thousand dollars to tens of thousands of dollars
for a feasibility study, depending on its depth and breadth, which in
turn depends on the project size and exactly what you need to know to
move forward with your project. Rarely, however, is the cost more than
1 percent of overall project costs, and often it is far less.
Schaedler Yesco spent about $4,000 on the first study and $7,000 on
the second, which adds up to “a very, very tiny percentage”
of the projected $4 million cost of its warehouse-expansion project,
says Schaedler. “Even if we decided we were not going to stay
here, we had done the research to make the right decision.”
After spending $38,000 on a feasibility study, Town & Country Trust,
Baltimore, MD, decided not to move forward with an $8.5 million residential
apartment project on land it already owned. “When we compared
development costs with projected market rents, we felt the returns didn’t
justify the project,” which would have required extensive site
development, including retaining walls, as well as off-site improvements,
such as upgrading a road, explains Tony Conrad, Town & Country’s
vice president of acquisitions. The feasibility study “was pretty
extensive,” Conrad says. “It was the expertise we needed
to get to the ‘go or no-go’ decision.”
How a Feasibility Study Proceeds
In most feasibility studies, the first step is a land assessment by
an engineering firm to see whether the location is suitable for the
project. Ed Black, president of H. Edward Black and Associates, P.C.,
Harrisburg, PA, says that for every project, his civil engineering and
landscape architectural firm does “at least a short-form feasibility
study,” reviewing the client’s needs, the topography, and
government ordinances.
Black says that for some clients, the short-form study provides enough
information for them to decide whether or not to proceed with their
projects. But companies that need a more detailed analysis go further
to include more detailed site drawings and preliminary plans by an architect.
According to Frank Fox, president of Greenfield Architects, Ltd., Lancaster,
PA, the architect also provides specifications for building parts and
types of building materials, as well as a description of the facility’s
mechanical and electrical systems. These preliminary plan drawings and
specifications help establish a cost base, so the builder can then develop
a realistic statement of probable cost for your study, also taking into
account owner requirements, town ordinances, and land development needs.
A study’s other components include a preliminary schedule, which
covers the planning steps and timeframe from study completion to project
approval, and any off-site improvements required by the municipality,
such as adding a signalized intersection to accommodate traffic flow
to and from your facility.
Picking Your Feasibility Team
Involve a builder, architect, and engineer in your feasibility study,
rather than depending on just one discipline. An architectural firm
or contractor that pulls together a balanced team, by engaging each
professional only for the amount of work you need at each point in the
process, helps ensure that you don’t end up with too much depth
in one area and not enough information in another. You don’t want
to spend a lot of money on architectural detail, for example, before
you know if zoning or other site constraints will allow the type of
facility you need.
Ask a builder or architect to show you examples of feasibility studies
they’ve conducted. Eliminate aspects that won’t be of use
to you and include or amplify areas that will help answer your specific
questions. Once you choose the company or firm to conduct your study,
share everything you know about the project, as well as your questions—and
be available throughout the study to answer their questions.
If you’re considering a design-builder to conduct your feasibility
study, choose one who won’t lock you into a long-term relationship.
It’s usually more advantageous in the long run to pay for a study
you will own, rather than accept an inexpensive or free study that locks
you into using a specific contractor. Even if you choose not to go forward
with the project, you can in the future reuse many portions of a feasibility
study with relatively minor adjustments, should you decide to reconsider
the facility plan or revisit a potential site. 